| Project Bond |
Featured Project
Project Bond
We start work in November 2008 on a high profile scheme to construct the foundations for a new production plant at IDX, Wexford.
Project Bond will see the creation of a new factory, utility and administration buildings and we have been commissioned by Dublin-based Project Management.
The €1.5 million contract will run for three months and is a mixed piling scheme involving the installation of some 232 450mm diameter CFA piles and 1,225 270mm square precast concrete piles.
Work gets underway in late November and FK Lowry will be using two PM20 piling rigs and a CM48 rig to deliver the works on site.
|